
A Partnership with Soprema in Sherbrooke (QC)
Introduction
SOPREMA (Canada) has been recycling polystyrene (PS) since 2018. This recycled material, a type of plastic with the number 6 recycling symbol, is used to manufacture extruded polystyrene (XPS) thermal insulation at their Sherbrooke plant in Québec. To meet growing demand from the construction and renovation industry, the company recycled over 10,000 tonnes of PS in 2023. It is expecting an increase in demand to meet growing needs over the next few years [1].
In order to contribute to circular economy initiatives and thereby increase its supply of recycled raw materials, SOPREMA supports several companies and municipalities wishing to recycle their PS locally. A case in point is the Granby Ecocentre in Québec, which since March 2023 has been using hot densification equipment to optimize the recycling of approximately 20 tonnes of PS per year.
This case study outlines the key elements of this innovative project. It presents the main results of a comparative analysis between the recycling of non-conditioned PS at the Ecocentre (without densification) and the recycling of conditioned PS (with densification). Other aspects of the project examined include the impact on energy consumption, time (labour), costs, the carbon footprint and storage space. Environmental and occupational health and safety (OHS) compliance issues are also discussed.
Project Description
The aim of the project is to collect and condition post-consumer PS from the Granby Ecocentre using a plastic densification process to optimize the processes leading to the recycling of this material, particularly in terms of ecocentre operations and transportation of materials to SOPREMA’s plant.
Project Partnership
Partner: Granby Ecocentre
Collaborator (City of Granby): Daniel Baril, general manager at the Corporation de gestion des matières résiduelles de La Haute-Yamaska
Recycler: SOPREMA plant in Sherbrooke
Collaborator (SOPREMA): Martin Olivier, recycled materials specialist at SOPREMA
Supplier (equipment): Foam Cycle and RecycleTech
Geographic and Demographic Context
Service cities: Granby (QC) and Waterloo (QC)
Region: Estrie
Population and density:
- Granby: 66,222 people (442/km2) [2]
- Waterloo: 4,410 people (370/km2) [3]
TOTAL: 70,632 people (416,9/km2)
Area:
- Granby: 15,610 ha (⇔ 156.1 km2) [2]
- Waterloo: 1,330 ha (⇔ 13.3 km2) [3]
TOTAL: 16,940 ha (⇔ 169.4 km2)
Opening hours (Ecocentre): 4 days a week (January to April) and 5 days a week (May to December), for a total of 32 weeks or 224 days a year
Traffic (Ecocentre): 100,000 visitors per year (2024)
Distance (from the Ecocentre to SOPREMA): 78 km (55 min) [4]
Targeted Recyclable Material
Accepted materials: Polystyrene bearing the No. 6 recycling symbol, such as the following products:
- Thermal insulation,
- Food containers,
- Storage containers,
- Foam flower pots (white),
- Food trays (all colours).
Refused materials: All other plastics as well as certain PS materials containing other plastics with the #6 recycling symbol, such as the following products:
- Yogurt containers,
- Rigid flower pots (black),
- Soft objects (e.g. pool floats),
- CD covers,
- Objects soiled by any of the contaminants listed below.
Current volume (recycled PS): 20 Mt/year
Potential volume (recyclable PS): 40 Mt/year
Current contamination rate: 3% on average
Acceptable contamination level: 5% max
Observed contaminants: Inorganic materials from storage (e.g. dust, sand, earth and stone)
Contaminants to avoid: Concrete, cement, earth, metals, wood, cardboard, hazardous substances and other types of plastic


Examples of accepted PS materials


Examples of refused PS materials
Conditioning Equipment (Densification)
Commissioning date: March 2023
Delivery lead time: The machine delivery lead time is 3 to 5 months
Conditioning equipment: RecycleTech EPS Densifier XT200


PS material densification equipment


PS material densification equipment control panel
Description of Scenarios
Two scenarios were developed to analyze the impact of the project, comparing the Granby Ecocentre’s plan to recycle conditioned PS (with densification) with the recycling of non-conditioned polystyrene (without densification). The various scenario parameters are also described in relation to ecocentre operations and the transportation of materials to SOPREMA’s facilities.
In both cases, residents as well as eligible industries, businesses and institutions (ICI) bring their PS materials to the Ecocentre, which manages the collection and processing of the materials. SOPREMA handles the transportation logistics and then recycles the materials at its Sherbrooke plant for the manufacture of XPS thermal insulation.
Non-Conditioned Polystyrene
(Without Densification)
The “non-conditioned polystyrene” scenario corresponds to ecocentre activities solely involving the collection and transportation of materials, without any processing or conditioning.
Conditioned Polystyrene
(With Densification)
The “conditioned polystyrene” scenario corresponds to ecocentre activities involving the collection, conditioning and transportation of materials, including densification for further processing.


Bags with non-conditioned PS materials


Pallets with conditioned PS materials
Various parameters, such as energy consumption, labour time, costs, carbon footprint and storage space, are used to compare the two scenarios. In order to better understand the differences between the scenarios, these parameters are explained first in terms of ecocentre operations and then in terms of transportation to SOPREMA’s facilities. The analysis period is based on a full year, from June 2023 to June 2024.
Stages and Participants
The participants and stages presented below apply to both scenarios, with the exception of the PS conditioning stage, which applies only to the “conditioned polystyrene” scenario.
- Polystyrene collection: Residents and eligible ICI organizations are invited to voluntarily bring their PS materials to the Ecocentre during opening hours. The materials will then be directed to the sorting station by ecocentre employees who can also advise visitors and answer any questions they may have.
- Sorting of materials: Residents and ICI organizations must ensure that only accepted materials are dropped off. They must also ensure that materials are properly sorted according to the instructions on the signs on the recycling bins. As a general rule, sorting is done according to colour. Ecocentre employees then check that the sorting has been done correctly, and make any necessary sorting adjustments, if necessary. Refused materials are placed in the waste container.
- Material conditioning: Ecocentre employees take the accepted materials and feed them into the densifier for conditioning. No resident or ICI individual has access to the PS densification area. Conditioned materials are then put into a large bag, which is then placed on a standard pallet for easy handling.
- Transportation of materials: Ecocentre employees load a truck to transport conditioned materials to SOPREMA’s facilities. The company then handles the logistics and transportation of the materials from the Ecocentre to its plant in Sherbrooke.
- Material recycling: SOPREMA crushes and processes materials at its Sherbrooke plant. This first step involves extruding the plastic beads. These are then mixed into the recipes used to manufacture XPS insulation panels.
Ecocentre Operations
For the collection and management of PS materials, the various scenarios relating to the operations of the Granby Ecocentre take into account that the materials in question were collected and handled under the following conditions:
Scenario Comparison – Operations (Ecocentre)
Non-Conditioned Polystyrene | Conditioned Polystyrene | |
---|---|---|
Energy consumption and carbon footprint (equipment)1 | 760 kWh for electricity (lift truck) | 3,290 kWh for electricity (machine) and 50 kWh for electricity (lift truck) |
Operating and maintenance costs (equipment)2 | $418 for electricity (lift truck) | $2,567 for electricity (machine), $100 for maintenance (machine) and $28 for electricity (lift truck) |
Time and cost of operations (labour)3 | Employee(s) working 152 hours per year ($3,040) | Employee(s) working 276 hours per year ($5,520) |
Storage space4 | Storage of materials indoors or outdoors (sheltered from the elements) with a surface area of 0.091 m2/kg (⇔ 0.444 ft2/lb) | Storage of materials indoors or outdoors (sheltered from the elements) with a surface area of 0.007 m2/kg (⇔ 0.036 ft2/lb) |
1, 2, 3, 4 For methodology and calculation parameters, ask for the full case study available on request.
Transportation to SOPREMA’s Facilities
For the transportation of PS, the various scenarios relating to transportation from the Granby Ecocentre to SOPREMA’s facilities take into account that the materials in question were transported under the following conditions:
Scenario Comparison – Transportation (To SOPREMA)
Non-Conditioned Polystyrene | Conditioned Polystyrene | |
---|---|---|
Energy consumption and carbon footprint5 | 12,609 kWh of electricity (⇔ 1,778 litres of diesel) | 1,009 kWh of electricity (⇔ 142 litres of diesel) |
Capacity (per load)6, 7 | 408 kg (⇔ 900 lb), equivalent to 60 to 70 bags per load | 13,154 kg (⇔ 29,000 lb), equivalent to 10 pallets per load |
Frequency (number of trips), distance (km) and cost ($)8 | Approximately 1 shipment per week, representing more than 50 trips and a total distance of 3,900 km per year. The cost of transportation is $600 per trip. | Approximately 1 shipment per quarter, representing less than 4 trips and a total distance of 312 km per year. The cost of transportation is $600 per trip. |
5, 6, 7, 8 For methodology and calculation parameters, ask for the full case study available on request.
Analysis Results
The results of the analysis show the impact of the different scenarios in terms of energy consumption, labour time, costs, carbon footprint and storage space. It’s worth remembering that the volume of recycled PS is 20 tonnes for the period in question.
Energy Consumption
The table below compares the energy consumption of the two scenarios on an annual basis. Overall, conditioned PS requires 8,886 kWh less than non-conditioned PS, corresponding to a reduction of around 66%. This represents savings of 88,865 kWh over 10 years. The difference is mainly due to the fact that the amount of energy required to transport conditioned PS to SOPREMA’s facilities is much lower.


Labour Time
The table below compares the time and labour required for the two scenarios on an annual basis. For the Ecocentre, conditioned PS requires 124 hours more than non-conditioned PS, corresponding to an increase of around 182%. The use of the densification equipment explains this increase. Nonetheless, time is saved in terms of material handling and preparation for transportation of materials.


Cost
The table below compares the costs of the two scenarios on an annual basis. For the Ecocentre, conditioned PS requires $26,000 less than non-conditioned PS, corresponding to a reduction of around 78%. This represents savings of $260,000 over 10 years. The difference is mainly due to the fact that transportation costs for conditioned materials are reduced and entirely borne by SOPREMA. Nevertheless, the labour cost of conditioned PS is greater than that of non-conditioned PS, reducing potential savings.


Carbon Footprint
The table below compares the carbon footprint of the two scenarios on an annual basis. Overall, conditioned PS accounts for 4,446 kgCO2eq. less than non-conditioned PS, corresponding to a reduction of around 92%. This represents around 44,446 kgCO2eq. avoided over 10 years. The difference is mainly due to the fact that the carbon footprint of transporting conditioned materials is much lower.


Storage Space
The table below compares the storage space required in the two scenarios on an annual basis. Overall, conditioned PS requires 1,695 m2 (⇔ 18,240 ft2) less than non-conditioned PS, corresponding to a reduction of around 91%. The difference is mainly due to the much smaller space required for conditioned materials storage and handling.


Compliance with Québec Laws and Regulations
Québec’s legislation includes a number of laws and regulations that apply to ecocentre operations. It is important that polystyrene (PS) collection and conditioning activities comply with the relevant requirements. For these reasons, the relevant environmental and occupational health and safety (OHS) compliance aspects are addressed in this section.
Occupational Health and Safety
With regard to OHS compliance, certain conditions may apply to ecocentres carrying out PS densification activities on their site. In the interest of OHS risk prevention, SOPREMA requested an expert opinion from the Commission des normes, de l’équité, de la santé et de la sécurité du travail (CNESST) concerning the requirements to be met, more specifically with regard to the following provisions:
- Act Respecting Occupational Health and Safety, RLRQ, S-2.1
- Regulation Respecting Occupational Health and Safety, RLRQ, S-2.1, r. 13
This opinion is based on the CNESST visit carried out in June 2024 and deals with densification equipment operated at the Granby Ecocentre [7]. This section presents the main findings of the CNESST report, and includes some of SOPREMA’s recommendations.
Aspects: Odour
Findings of the CNESST Report
At the time of the visit, the operation of the machine did not give off any particular odours, and the operator did not seem to feel any discomfort. Exposure time was short, and good air circulation was ensured. The ventilation system seemed adequate.
SOPREMA’s Recommendations
Some materials may give off odours during densification. Therefore, when using a machine indoors, it is recommended to include a ventilation system to ensure a constant change of air in the area while the machine is in use.9
Aspects: Smoke and fumes
Findings of the CNESST Report
At the time of the visit, the machine was emitting smoke and fumes from the heating of the materials. These were captured by mechanical suction directly at the source of the machine and vented to the outside.
SOPREMA’s Recommendations
During densification, it is normal to generate light smoke and fumes resulting from the heating of the materials. Therefore, when using a machine indoors, it is recommended to include a mechanical extraction system directly at the source of the machine to discharge smoke and fumes outside.
Aspects: Personal protective equipment (PPE)
Findings of the CNESST Report
At the time of the visit, an operating procedure was displayed next to the machine. It showed that the employee operating the machine must use certain PPE, such as safety glasses, cut-resistant gloves and ear muffs.8
SOPREMA’s Recommendations
The use of PPE, such as safety glasses10, cut-resistant gloves11 and ear muffs12, is recommended as an additional means of protection. It is imperative to post the procedure and train employees handling the materials and operating the machine.
8, 9, 10, 11, 12 For compliance information, ask for the full case study available on request.


Examples of PPE to be used by ecocentre employees operating the densification equipment


Example of a ventilation system inside the container housing the densification equipment
Environmental
With regard to environmental compliance, certain conditions may apply to ecocentres carrying out PS densification activities on their site. In order to clarify this issue, SOPREMA requested a legal opinion from the Sodavex law firm concerning the requirements to be met, more specifically with regard to the following provisions [8]:
- Environment Quality Act, RLRQ, c Q-2 (hereinafter the EQA)
- Regulation Respecting the Regulatory Scheme Applying to Activities on the Basis of Their Environmental Impact, RLRQ, c Q-2, r 17.1 (hereinafter REAFIE)
- Regulation Respecting the Reclamation of Residual Materials, RLRQ, c Q-2, r 49 (hereinafter RVMR)
- Regulation Respecting the Landfilling and Incineration of Residual Materials, RLRQ, c Q-2, r 19 (hereinafter REIMR)
As a general rule, it’s important to understand that requirements may vary depending on the status and history of each ecocentre. Given that the environmental authorization regime changed in 2018 and again in 2021, we need to take into account the requirements that prevailed before 2018, between 2018 and 2021 and since 2021 in order to cover the different situations that apply to ecocentres wishing to operate PS densification equipment13.
For the sake of simplicity, the above is a summary of the key facts contained in the legal opinion provided by the Sodavex law firm. To take into account the reality and specificities of each ecocentre, SOPREMA recommends always verifying and ensuring the environmental compliance of the site before installing PS densification equipment. The same logic also applies during the operating phase. Details of the opinion are available on request14.
13, 14 For compliance information, ask for the full case study available on request.
References
[1] SOPREMA Canada. (2024). Collection and Recycling of Residual Materials – Discover Our SOPRALOOP Process
[2] Google Maps. (2024). Directions: 1080 Rue André-Liné, Granby, QC to 5255 Rue Robert-Boyd, Sherbrooke, QC.
[3] City of Granby, Québec. (2024). General information about the city of Granby.
[4] City of Waterloo, Québec. (2024). General information about the city of Waterloo.
[5] Environment and Climate Change Canada. (2024). National Inventory Report, 1990–2022: Greenhouse Gas Sources and Sinks in Canada – Part 3.
[6] Environment and Climate Change Canada. (2024). National Inventory Report, 1990–2022: Greenhouse Gas Sources and Sinks in Canada – Part 2.
[7] CNESST. (2024). Rapport d’intervention en santé et sécurité du travail [RAP1473243] – June 21, 2024 visit to COGEMRHY: 1080, rue André-Liné, Granby, Québec.
[8] Sodavex. (2021). Legal opinion on the need to obtain ministerial authorization under the Environment Quality Act in order to carry out polystyrene densification.
Other Initiatives to Recycle Polystyrene Locally with SOPREMA
Val-Saint-François Regional County Municipality